Metric completed the planning, detailed design of all work disciplines, project management and construction supervision for the pipe jacking work of 60-m.-long r.c. tunnel from the Tire Recapping project site across the Industrial Estate’s road to Michelin Siam (NKE) factory for connection of utility systems between the two areas. It was an outstanding task in the project developed on a 30-rai land plot on that used to be a fiberglass factory. The scope of the project included the modification and renovation of an existing 4,000 sq.m. building for new tyre recapping workshop (reinforcing the existing building structure to satisfy the structural stability and new load carrying condition was also achieved), minor extension for new loading dock, pump house and cooling tower.
It also included the modification of roadways, drainage and sewer system